North Augusta High

North Augusta High

In November of 2015, we celebrated the completion of Phase 2A of construction and dedicated a 124,095-square-foot facility full of natural light and classrooms, a Freshman Academy, Media Center, Dining Room and Guidance Area.

In June of 2016, we celebrated the completion of Phase One of North Augusta High's new Math & Business Wing, a beautiful 45,610-square-foot, two-story facility, with a terrazzo floor entrance, seven business labs downstairs and three groups of paired science classrooms with labs and prep rooms on the second floor.

Phase 2B, which includes a brand new, two-story classroom wing for math, English, foreign language and social studies classes, was completed in October, 2019, clearing the way for the beginning of site prep and construction of Phase 3, which includes a new stadium-style basketball gymnasium.

Architect & Contractor Information

Architect: McMillan, Pazdan, Smith

Contractor: H.G. Reynolds

Delivery Method: Construction Management At Risk

  • Design Phases and Decisions with School Stakeholders’ Involvement

  • School Board and Office of School Facilities Approval of Each Phase 

  • Continual Building began in 2016.

Currently Under Construction Phase 3

Design:
Spring 2018

Construction and Substantial Completion:
August 2019 – November 2020

Total Estimated Project Cost:
$21 Million

Completed Phase 2b

Design:
January 2015 – December 2015

Construction and Substantial Completion:
July 2017 – November 2018

Total Estimated Project Cost:
$24.9 Million

Completed Phase 2a

Design:
January 2015 – December 2015

Construction:
March 2016 – July 2017

Total Estimated Project Cost:
$28.9 Million

Executive Summary Reports